6 judgments

Judgments

Delhi High Court Dismissed ·6 Nov 2026 ·Arbitration

Delhi HC: Interest Accrued on Fixed Deposit From Wrongfully Invoked Bank Guarantee Must Go to Contractor, Not DDA

The question: Whether the award, to the extent it denied the company the interest accrued on the fixed deposit made from the encashed performance bank guarantee, suffered from patent illegality warranting interference under Section 34

The Delhi High Court, sitting as a Bench of two Judges, has dismissed an appeal by the Delhi Development Authority against a Single Judge's order that modified an arbitral award. The award had held that DDA was not entitled to invoke the performance bank guarantee given by Jaksons Developers (P) Ltd, but had also said that the interest accrued on the fixed deposit holding the encashed amount would not be released to the company. The Single Judge set aside that part of the award. The Bench, in a judgment by Dr. Justice Aditi Choudhary, agreed that interest on the fixed deposit is the fruit of the principal and must follow it. DDA invited bids for a commercial plot at Twin District Towers, Rohini, for a hotel to house guests during the Commonwealth Games 2010. Jaksons Developers was the successful bidder and a Demand-cum-Allotment Letter was issued on 04.01.2008. The hotel had to be operational within twenty-four months of allotment. On 09.06.2008 the company furnished a performance bank guarantee of Rs. 9,30,00,000, equal to 5% of the bid amount, valid for four years under clause 3.14 of the tender document. Possession was given on 08.09.2008 and the conveyance deed was executed. In May 2010 DDA moved to invoke the guarantee for non-completion within twenty-four months. The company obtained an order under Section 9 of the Arbitration and Conciliation Act, 1996 on 09.06.2010 restraining invocation. The hotel was completed and made operational on 15.09.2010, DDA rejected the application for a completion or occupancy certificate on 21.09.2010, and limited term permission was granted on 29.09.2010. The hotel was used during the Games. An Arbitrator was appointed on 12.05.2011. On 22.10.2013 the Arbitrator, deciding an application under Section 17, vacated the restraint on condition that DDA keep the amount realised on encashment in a fixed deposit in a nationalised bank, to abide the outcome along with interest accrued. The award dated 25.04.2023, with an addendum of 21.05.2023, held DDA not entitled to invoke or encash the guarantee and directed release of Rs. 9,30,00,000 to the company. Claim No. 8 of the company, for 18% interest on the awarded amount, was rejected on the ground of delay attributable to both sides, the Chief Fire Officer and the Delhi Urban Arts Commission, and the addendum said the interest accrued on the guarantee would not be released to the company. DDA's counter claims, including one for interest on the guarantee amount, were all rejected. The company challenged the withheld interest under Section 34 (OMP (COMM) 349/2023). The Single Judge modified the award on 05.05.2026, and DDA appealed under Section 37(1)(c) read with Section 13(1A) of the Commercial Courts Act, 2015.

FAO(OS) (COMM) - 192/2026
Supreme Court ·6 Nov 2026 ·Constitutional ★ Editor's pick

Supreme Court holds National Book Trust is 'State' under Article 12, upholds the Full Bench ruling of Delhi High Court

The question: Whether the National Book Trust, India is 'State' within the meaning of Article 12 of the Constitution.

The Supreme Court has held that the National Book Trust, India is an 'other authority' under Article 12 of the Constitution and is therefore 'State' for the purposes of Part III. A Bench of Prashant Kumar Mishra and Augustine George Masih JJ dismissed the Trust's appeal and upheld the 2012 judgment of the Full Bench of the High Court of Delhi. The Bench said the only question before it was whether the Trust is 'State' under Article 12. It found that the Trust was created by Government resolutions, that the Government appoints its Chairman and nominates members of its governing bodies, and that its finances, accounts and rule changes are subject to Government involvement and approval. The Court held that these features, taken together, show control that is particular to the Trust and pervasive. The Court also made clear that the declaration does not make the Trust a Government department, does not make every employee a civil servant or confer on them all the Part XIV protections available to Government servants, and has no automatic consequence under Articles 309, 310 or 311. The appeal arose from a reference answered by the Full Bench of the High Court of Delhi in its judgment dated 01.06.2012. The Full Bench had examined the Trust on the principles in Ramana Dayaram Shetty, Ajay Hasia and Pradeep Kumar Biswas and concluded that the Government exercised deep and pervasive control over it, so that it was an instrumentality or alter ego of the Government. The Chairman of the Trust and another appellant challenged that conclusion in Civil Appeal No. 14369 of 2015. The Court heard counsel for the parties and Shri Sanjay Jain, senior counsel, who assisted as Amicus Curiae with Ms. Harshita Sukhija, counsel.

Civil Appeal No. 14369 of 2015 (2026 INSC 1202)
Supreme Court Allowed ·12 Oct 2026 ·Arbitration

Clauses name Delhi and Goa: Goa exclusive jurisdiction and Goa hearings make Goa the seat; Delhi High Court could not appoint arbitrator

The question: Whether Delhi or Goa is the juridical seat of arbitration when the arbitration clause mentions both places and the governing law clause gives exclusive jurisdiction to courts in Goa

The Supreme Court has held that where an arbitration clause names two places for the arbitration, one of them cannot automatically be treated as the juridical seat, and the governing law and jurisdiction clause of the agreement must be read to find the parties' intention. On that reading, the Bench of Justice Manoj Misra and Justice Vijay Bishnoi held that Goa was the seat and Delhi merely the venue, and that the Delhi High Court therefore had no jurisdiction to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The judgment is reported as 2026 INSC 1109. The dispute arose from a Franchise Agreement dated 3 August 2023 between Arcis Clean Energy Pvt. Ltd. and Parshva Innovation. Clause 32.4 of the arbitration clause said the precise location of the arbitration shall be within Delhi, while Clause 32.5 said the arbitration proceedings will be held in Goa. Clause 38 submitted the parties to the exclusive jurisdiction of the competent courts in Goa. The respondent proposed a sole arbitrator by notice of 25 March 2025. The appellant rejected the proposal on 19 April 2025. The respondent then moved the Delhi High Court, which by its order of 11 November 2025 appointed an arbitrator and left it to the arbitrator to choose the venue of hearings in consultation with the parties. The appellant came to the Supreme Court against that order. Leave was granted and the appeal was allowed.

C.A. No. 13663/2026
Gauhati High Court Partly allowed ·5 Oct 2026 ·Tender

Gauhati HC: IOCL to verify and revoke terminations of bulk LPG work orders where RC was uploaded as its 15.01.2026 note allowed; rest stand

The question: Whether termination of work orders for failure to submit the RC and amended PESO licence within four months of the LoA was valid.

Justice Kaushik Goswami of the Gauhati High Court partly allowed seven writ petitions under Article 226 challenging the termination orders of 11.05.2026 by which work orders for transportation of bulk LPG in Assam and Meghalaya were terminated by Indian Oil Corporation Limited (IOCL). The Court held that termination was unsustainable for bidders who had uploaded the updated Registration Certificate (RC) of their Agreement to Sale (ATS) tank trucks, with the PESO amendment application or an expected completion date, by 21:00 hours on 15.01.2026, because the Corporation itself had carved out that relaxation in its final reminder e-mail of 15.01.2026 and the termination orders did not consider it. Bidders who did not upload the updated RC by that deadline got no relief. The petitions are WP(C) Nos. 2747/2026 (Gaman Sarkar), 2749/2026 (Ramkrishna Sutradhar), 2750/2026 (Balo Ram Kaibarta), 2751/2026 (M/s Pallab Saikia), 2753/2026 (Laxmi Transport), 2754/2026 (Juri Thakuria) and 2755/2026 (Suresh Rabha). All arise from NIT No. LPG/BULK/TT/IOC/AS/2025-30 dated 01.03.2025. Corrigendum No. 3 dated 04.04.2025 let a bidder offer tank trucks still running under the existing contract through an ATS, but required the RC transfer and amended PESO licence within four months of the Letter of Acceptance (LoA), failing which the trucks could be terminated, and said the timeline would not be extended under any circumstances. The petitioners were issued LoAs on 16.09.2025, so the period ended on 15.01.2026. Work orders followed and they began operating. Show-cause notices were issued on 05.03.2026 and the vehicles were suspended. After WP(C) No. 1526/2026 was disposed of on 27.04.2026 with a direction to decide their replies, IOCL terminated the work orders on 11.05.2026.

WP(C)/2749/2026
Delhi High Court Partly allowed ·28 Sep 2026 ·Arbitration

Delhi HC: Arbitrator's refusal of price variation despite the contract's formula is patent illegality; award partly set aside

The question: Did the arbitrator act against the contract's own terms in rejecting price variation for the original contract period?

The Delhi High Court has set aside part of an arbitral award in a road-bridge contract with the New Okhla Industrial Development Authority (NOIDA), holding that the arbitrator's refusal of the contractor's price variation claim was patently illegal because it ignored what the contract itself provides. Justice Mini Pushkarna held that the contract allowed price variation both for the original period and for an extension caused by the contractor's own delay, and that the arbitrator had in effect rewritten the contract. The Court, however, upheld his finding that the delay was the contractor's fault. Dwarika Projects Ltd. won a tender for the construction of Bridge No. 2 on an irrigation drain between Sectors 78 and 49, Noida, under a contract of 7 December 2009 that required completion within twelve months. The work finished much later, and each side blamed the other. The sole arbitrator's award of 10 December 2018 awarded the contractor Rs 1,02,95,056 on Claims 1, 2 (in part) and 3, with interest and costs, but rejected Claims 4 to 10. The contractor's petition under Section 34 of the Arbitration and Conciliation Act, 1996 was finally confined to Claim 4, its claim of Rs 2,29,43,350 for price variation. The Court set the award aside to that extent and left the parties free to start fresh arbitration to work out the amount.

O.M.P. (COMM)/182/2019
Supreme Court Allowed ·30 Sep 2026 ·Government Contracts

Supreme Court: A State cannot recover alleged overpayment on old works from a contractor's bills under separate contracts

The question: Is the recovery order traceable to any clause of the contract that lets the State recover dues of one contract from payments under another?

The Supreme Court on 30 September 2026 quashed a recovery order by which a Chhattisgarh road agency had deducted Rs 84,17,003 from a contractor's bills on three ongoing road projects to make good an alleged overpayment on two earlier, separate contracts. A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe (judgment by Justice Aradhe) held that none of the contract clauses relied on by the State permitted this, and that the order was passed without notice, in breach of natural justice. It directed the State to release the amount with 6 per cent interest. The appellant, M/s Awadhesh Singh Gautam, a partnership firm, was awarded three packages under the Pradhan Mantri Gram Sadak Yojana by the Chhattisgarh Rural Road Development Agency (CGRRDA), with work orders of 1 September 2023 and 5 November 2024. After doing about 40 per cent of each, it raised running bills of Rs 39,78,500, Rs 45,62,000 and Rs 23,55,000, which stayed unpaid despite reminders in September 2025. Separately, on 3 January 2023, it had been given two other road contracts of about Rs 437.43 lakh. After complaints of irregularities, a five-member committee appointed by the Collector, South Bastar, Dantewada, reported on 9 January 2024 that Rs 3,55,82,055 had been paid for those earlier works against work of only about Rs 1,54,75,938, an excess of Rs 2,01,06,117. It recommended recovery, blacklisting and a probe. A demand note issued under Section 146 of the Chhattisgarh Land Revenue Code, 1959 was quashed by the High Court on 5 March 2025 for want of notice or hearing, leaving the State free to act afresh in accordance with law. An FIR was registered under Sections 420, 467, 468, 471, 409 and 120-B of the Indian Penal Code against a partner of the firm and CGRRDA officers, and a chargesheet was filed on 30 December 2025. Independently, the Executive Engineer of the Project Implementation Unit passed a recovery order on 27 September 2025, blocking Rs 84,17,003 out of the amounts payable and deducting Rs 28,00,000, Rs 38,00,000 and Rs 18,17,003 from the three subsequent works. The firm's representation of 9 October 2025 drew no response, and the High Court on 7 January 2026 dismissed its three writ petitions, saying disputed questions of fact could not be decided under Article 226.

C.A. No. 13299/2026