Subscribe

Latest › Delhi High Court › Civil › Contract & Commercial › 6 November 2026

Delhi High Court Notable

Delhi HC: Interest Accrued on Fixed Deposit From Wrongfully Invoked Bank Guarantee Must Go to Contractor, Not DDA

Court
High Court of Delhi
Date of judgment
6 November 2026
Case
FAO(OS) (COMM) - 192/2026
Parties
DELHI DEVELOPMENT AUTHORITY Vs JAKSONS DEVELOPERS (P) LTD THROUGH ITS AUTHORISED SIGNATORY SHRI PEAYUSH AGARWAL, CEO
Bench
Justice Dinesh Mehta, Dr Justice Aditi Choudhary
Outcome
Dismissed

The court's decision

The Bench began with the limits of review. Relying on MMTC Ltd. v. Vedanta Ltd. and Somdatt Builders-NCC-NEC (JV) v. National Highways Authority of India, it noted that a court under Section 34 does not sit in appeal over an award, and that interference under Section 37 cannot travel beyond the restrictions in Section 34. The question was whether the Single Judge exceeded his jurisdiction in modifying the award.

On the Section 17 order, the Bench read the direction that the amount along with interest would abide the outcome as an interim measure to protect the parties depending on the final result. The Arbitrator had allowed encashment but did not let DDA use the money, and ordered a fixed deposit so that the principal sum earned interest in the meantime. The purpose was that the fixed deposit, principal and interest, go to the party found entitled to the guarantee. That condition was defeated if DDA kept the interest after it was finally held not entitled to invoke or encash the guarantee. Central Bank of India v. Ravindra was held distinguishable on facts, since it relates to the law governing the debtor and creditor and the meaning of 'the principal sum adjudged' in Section 34 of the Code of Civil Procedure, 1908 in money-recovery suits, especially by banks against borrowers.

On interest, the Bench noted that DDA's Counter Claim No. 2 for interest on the guarantee amount was rejected because DDA was held not entitled to invoke the guarantee. It remained unexplained how DDA could keep the benefit of that guarantee by way of interest on the fixed deposit. The award recorded no reasoned finding for denying the interest to the company, and the two findings were mutually contradictory: the rejection of DDA's counter claims for invocation and interest sat against DDA indirectly keeping the interest on the deposit. Claim No. 8 was decided under Section 31(7), but the encashed guarantee amount was not an amount awarded or 'the sum for which the award is made'; it was given to the company because DDA could not invoke the guarantee. Section 31(7) therefore could not be extended to the interest on the fixed deposit, and withholding it on the strength of the rejection of Claim No. 8 was against the statute and a patent illegality.

On severance, the Bench quoted Gayatri Balasamy and rejected DDA's argument, holding that interest on the fixed deposit was not part of Claim No. 8, which was for 18% interest on the awarded amount. The part of the award directing release of Rs. 9,30,00,000 and the direction not to release the interest on the fixed deposit were severable and not dependent on the other claim awarded. The interest of the fixed deposit was nothing but the fruit of the principal, and since the principal was ordered to be given to the company, the interest as a natural corollary should also go to it.

The Bench said it was not inclined to interfere with the judgment of 05.05.2026. The appeal was dismissed and the pending applications were disposed of.

Summary

The Delhi High Court, sitting as a Bench of two Judges, has dismissed an appeal by the Delhi Development Authority against a Single Judge's order that modified an arbitral award. The award had held that DDA was not entitled to invoke the performance bank guarantee given by Jaksons Developers (P) Ltd, but had also said that the interest accrued on the fixed deposit holding the encashed amount would not be released to the company. The Single Judge set aside that part of the award. The Bench, in a judgment by Dr. Justice Aditi Choudhary, agreed that interest on the fixed deposit is the fruit of the principal and must follow it.

DDA invited bids for a commercial plot at Twin District Towers, Rohini, for a hotel to house guests during the Commonwealth Games 2010. Jaksons Developers was the successful bidder and a Demand-cum-Allotment Letter was issued on 04.01.2008. The hotel had to be operational within twenty-four months of allotment. On 09.06.2008 the company furnished a performance bank guarantee of Rs. 9,30,00,000, equal to 5% of the bid amount, valid for four years under clause 3.14 of the tender document. Possession was given on 08.09.2008 and the conveyance deed was executed.

In May 2010 DDA moved to invoke the guarantee for non-completion within twenty-four months. The company obtained an order under Section 9 of the Arbitration and Conciliation Act, 1996 on 09.06.2010 restraining invocation. The hotel was completed and made operational on 15.09.2010, DDA rejected the application for a completion or occupancy certificate on 21.09.2010, and limited term permission was granted on 29.09.2010. The hotel was used during the Games. An Arbitrator was appointed on 12.05.2011. On 22.10.2013 the Arbitrator, deciding an application under Section 17, vacated the restraint on condition that DDA keep the amount realised on encashment in a fixed deposit in a nationalised bank, to abide the outcome along with interest accrued.

The award dated 25.04.2023, with an addendum of 21.05.2023, held DDA not entitled to invoke or encash the guarantee and directed release of Rs. 9,30,00,000 to the company. Claim No. 8 of the company, for 18% interest on the awarded amount, was rejected on the ground of delay attributable to both sides, the Chief Fire Officer and the Delhi Urban Arts Commission, and the addendum said the interest accrued on the guarantee would not be released to the company. DDA's counter claims, including one for interest on the guarantee amount, were all rejected. The company challenged the withheld interest under Section 34 (OMP (COMM) 349/2023). The Single Judge modified the award on 05.05.2026, and DDA appealed under Section 37(1)(c) read with Section 13(1A) of the Commercial Courts Act, 2015.

The question before the court

What each side argued

Precedents referred to

Provisions referred to

Read the full judgment (PDF) ↗

Official source: High Court of Delhi. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

ArbitrationBank GuaranteeCommercial Law

Related judgments

Supreme Court Allowed ·12 Oct 2026 ·Arbitration

Clauses name Delhi and Goa: Goa exclusive jurisdiction and Goa hearings make Goa the seat; Delhi High Court could not appoint arbitrator

The question: Whether Delhi or Goa is the juridical seat of arbitration when the arbitration clause mentions both places and the governing law clause gives exclusive jurisdiction to courts in Goa

The Supreme Court has held that where an arbitration clause names two places for the arbitration, one of them cannot automatically be treated as the juridical seat, and the governing law and jurisdiction clause of the agreement must be read to find the parties' intention. On that reading, the Bench of Justice Manoj Misra and Justice Vijay Bishnoi held that Goa was the seat and Delhi merely the venue, and that the Delhi High Court therefore had no jurisdiction to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The judgment is reported as 2026 INSC 1109. The dispute arose from a Franchise Agreement dated 3 August 2023 between Arcis Clean Energy Pvt. Ltd. and Parshva Innovation. Clause 32.4 of the arbitration clause said the precise location of the arbitration shall be within Delhi, while Clause 32.5 said the arbitration proceedings will be held in Goa. Clause 38 submitted the parties to the exclusive jurisdiction of the competent courts in Goa. The respondent proposed a sole arbitrator by notice of 25 March 2025. The appellant rejected the proposal on 19 April 2025. The respondent then moved the Delhi High Court, which by its order of 11 November 2025 appointed an arbitrator and left it to the arbitrator to choose the venue of hearings in consultation with the parties. The appellant came to the Supreme Court against that order. Leave was granted and the appeal was allowed.

C.A. No. 13663/2026
Delhi High Court Partly allowed ·28 Sep 2026 ·Arbitration

Delhi HC: Arbitrator's refusal of price variation despite the contract's formula is patent illegality; award partly set aside

The question: Did the arbitrator act against the contract's own terms in rejecting price variation for the original contract period?

The Delhi High Court has set aside part of an arbitral award in a road-bridge contract with the New Okhla Industrial Development Authority (NOIDA), holding that the arbitrator's refusal of the contractor's price variation claim was patently illegal because it ignored what the contract itself provides. Justice Mini Pushkarna held that the contract allowed price variation both for the original period and for an extension caused by the contractor's own delay, and that the arbitrator had in effect rewritten the contract. The Court, however, upheld his finding that the delay was the contractor's fault. Dwarika Projects Ltd. won a tender for the construction of Bridge No. 2 on an irrigation drain between Sectors 78 and 49, Noida, under a contract of 7 December 2009 that required completion within twelve months. The work finished much later, and each side blamed the other. The sole arbitrator's award of 10 December 2018 awarded the contractor Rs 1,02,95,056 on Claims 1, 2 (in part) and 3, with interest and costs, but rejected Claims 4 to 10. The contractor's petition under Section 34 of the Arbitration and Conciliation Act, 1996 was finally confined to Claim 4, its claim of Rs 2,29,43,350 for price variation. The Court set the award aside to that extent and left the parties free to start fresh arbitration to work out the amount.

O.M.P. (COMM)/182/2019
Supreme Court ·6 Nov 2026 ·Hindu Law ★ Editor's pick

Grandson Cannot Claim Birthright In Property Father Received From Grandfather's Estate: Supreme Court

The question: Whether a minor son can claim a half share, as a coparcener by birth, in property his father, then alive, obtained on partition of the grandfather's estate.

The Supreme Court has dismissed a civil appeal by a minor, suing through his mother as natural guardian, who claimed a half share by birth in land that his father, then alive, had received in a family partition. The Bench of Justice Augustine George Masih and Justice Sunita Agarwal held that the grandfather's property devolved on his Class I heirs under Section 8 of the Hindu Succession Act, 1956, that a son's son is not a Class I heir, and that once the heirs partitioned the property each took his or her share as exclusive owner and not as a coparcenary holding. The suit, Original Suit No. 1698 of 1997, sought partition and possession of a half share in 1811 sq. ft. of land. The plaint said the land was joint family property of the minor's grandfather and had been inherited by the minor along with his father, the first defendant. The father's sister had filed C.S. No. 1728 of 1993 for partition of the grandfather's property, and it was decreed on a compromise dated 03.02.1994, under which the father received the land. The minor was born on 06.01.1994. The father sold the land to defendant nos. 2 and 3 by sale deeds dated 03.04.1997 and 17.04.1997. The plaint did not challenge the compromise decree or the sale deeds. The II Additional Judge, City Civil Court, Chennai passed a preliminary decree of partition. The purchasers appealed and the preliminary decree was set aside. The appellant came to the Supreme Court against the judgment and order dated 11.08.2010 of the High Court. The father remained ex parte, as recorded in the submissions, and died in 2024.

Civil Appeal No. 7020 of 2012 (2026 INSC 1208)