Latest › Delhi High Court › Civil › Contract & Commercial › 6 November 2026
Delhi HC: Interest Accrued on Fixed Deposit From Wrongfully Invoked Bank Guarantee Must Go to Contractor, Not DDA
- Court
- High Court of Delhi
- Date of judgment
- 6 November 2026
- Case
- FAO(OS) (COMM) - 192/2026
- Parties
- DELHI DEVELOPMENT AUTHORITY Vs JAKSONS DEVELOPERS (P) LTD THROUGH ITS AUTHORISED SIGNATORY SHRI PEAYUSH AGARWAL, CEO
- Bench
- Justice Dinesh Mehta, Dr Justice Aditi Choudhary
- Outcome
- Dismissed
The court's decision
The Bench began with the limits of review. Relying on MMTC Ltd. v. Vedanta Ltd. and Somdatt Builders-NCC-NEC (JV) v. National Highways Authority of India, it noted that a court under Section 34 does not sit in appeal over an award, and that interference under Section 37 cannot travel beyond the restrictions in Section 34. The question was whether the Single Judge exceeded his jurisdiction in modifying the award.
On the Section 17 order, the Bench read the direction that the amount along with interest would abide the outcome as an interim measure to protect the parties depending on the final result. The Arbitrator had allowed encashment but did not let DDA use the money, and ordered a fixed deposit so that the principal sum earned interest in the meantime. The purpose was that the fixed deposit, principal and interest, go to the party found entitled to the guarantee. That condition was defeated if DDA kept the interest after it was finally held not entitled to invoke or encash the guarantee. Central Bank of India v. Ravindra was held distinguishable on facts, since it relates to the law governing the debtor and creditor and the meaning of 'the principal sum adjudged' in Section 34 of the Code of Civil Procedure, 1908 in money-recovery suits, especially by banks against borrowers.
On interest, the Bench noted that DDA's Counter Claim No. 2 for interest on the guarantee amount was rejected because DDA was held not entitled to invoke the guarantee. It remained unexplained how DDA could keep the benefit of that guarantee by way of interest on the fixed deposit. The award recorded no reasoned finding for denying the interest to the company, and the two findings were mutually contradictory: the rejection of DDA's counter claims for invocation and interest sat against DDA indirectly keeping the interest on the deposit. Claim No. 8 was decided under Section 31(7), but the encashed guarantee amount was not an amount awarded or 'the sum for which the award is made'; it was given to the company because DDA could not invoke the guarantee. Section 31(7) therefore could not be extended to the interest on the fixed deposit, and withholding it on the strength of the rejection of Claim No. 8 was against the statute and a patent illegality.
On severance, the Bench quoted Gayatri Balasamy and rejected DDA's argument, holding that interest on the fixed deposit was not part of Claim No. 8, which was for 18% interest on the awarded amount. The part of the award directing release of Rs. 9,30,00,000 and the direction not to release the interest on the fixed deposit were severable and not dependent on the other claim awarded. The interest of the fixed deposit was nothing but the fruit of the principal, and since the principal was ordered to be given to the company, the interest as a natural corollary should also go to it.
The Bench said it was not inclined to interfere with the judgment of 05.05.2026. The appeal was dismissed and the pending applications were disposed of.
Summary
The Delhi High Court, sitting as a Bench of two Judges, has dismissed an appeal by the Delhi Development Authority against a Single Judge's order that modified an arbitral award. The award had held that DDA was not entitled to invoke the performance bank guarantee given by Jaksons Developers (P) Ltd, but had also said that the interest accrued on the fixed deposit holding the encashed amount would not be released to the company. The Single Judge set aside that part of the award. The Bench, in a judgment by Dr. Justice Aditi Choudhary, agreed that interest on the fixed deposit is the fruit of the principal and must follow it.
DDA invited bids for a commercial plot at Twin District Towers, Rohini, for a hotel to house guests during the Commonwealth Games 2010. Jaksons Developers was the successful bidder and a Demand-cum-Allotment Letter was issued on 04.01.2008. The hotel had to be operational within twenty-four months of allotment. On 09.06.2008 the company furnished a performance bank guarantee of Rs. 9,30,00,000, equal to 5% of the bid amount, valid for four years under clause 3.14 of the tender document. Possession was given on 08.09.2008 and the conveyance deed was executed.
In May 2010 DDA moved to invoke the guarantee for non-completion within twenty-four months. The company obtained an order under Section 9 of the Arbitration and Conciliation Act, 1996 on 09.06.2010 restraining invocation. The hotel was completed and made operational on 15.09.2010, DDA rejected the application for a completion or occupancy certificate on 21.09.2010, and limited term permission was granted on 29.09.2010. The hotel was used during the Games. An Arbitrator was appointed on 12.05.2011. On 22.10.2013 the Arbitrator, deciding an application under Section 17, vacated the restraint on condition that DDA keep the amount realised on encashment in a fixed deposit in a nationalised bank, to abide the outcome along with interest accrued.
The award dated 25.04.2023, with an addendum of 21.05.2023, held DDA not entitled to invoke or encash the guarantee and directed release of Rs. 9,30,00,000 to the company. Claim No. 8 of the company, for 18% interest on the awarded amount, was rejected on the ground of delay attributable to both sides, the Chief Fire Officer and the Delhi Urban Arts Commission, and the addendum said the interest accrued on the guarantee would not be released to the company. DDA's counter claims, including one for interest on the guarantee amount, were all rejected. The company challenged the withheld interest under Section 34 (OMP (COMM) 349/2023). The Single Judge modified the award on 05.05.2026, and DDA appealed under Section 37(1)(c) read with Section 13(1A) of the Commercial Courts Act, 2015.
The question before the court
- Whether the award, to the extent it denied the company the interest accrued on the fixed deposit made from the encashed performance bank guarantee, suffered from patent illegality warranting interference under Section 34
- Whether Section 31(7) of the Arbitration Act governed that interest
- Whether the Single Judge could modify the award by setting aside only that part, and whether the Section 37 appeal court could interfere
What each side argued
- For DDA: the Single Judge relied on Central Bank of India v. Ravindra, which arose in a bank and borrower setting on capitalisation of interest and has no application to interest on a fixed deposit kept under a Section 17 order; the Section 17 order of 22.10.2013 only preserved the corpus and did not decide entitlement to interest.
- For DDA: the direction to release Rs. 9,30,00,000 was a money award, so pre-award interest fell within the Arbitrator's discretion under Section 31(7)(a), and his reasoned finding of mutual delay, expressed through Claim No. 8 and the addendum, was a plausible view that could not be treated as patent illegality.
- For DDA: under Gayatri Balasamy v. ISG Novasoft Technologies Ltd., the severance power in the proviso to Section 34(2)(a)(iv) covers only parts of an award dealing with matters not submitted to arbitration, and interest on the fixed deposit was part of Claim No. 8, which was adjudicated and rejected.
- For the company: the guarantee was encashed and placed in a fixed deposit so that the interest could go to the party who succeeded on the guarantee, Section 31(7) had no application as no payment of money was awarded, and the Arbitrator wrongly mixed up Claim No. 8 with interest accrued on the guarantee amount.
- For the company: DDA could not keep the interest on a guarantee it had wrongly invoked, as that would let it gain from its own wrong, and there was no reason to give the interest to DDA when its counter claims were rejected.
Precedents referred to
- Central Bank of India v. Ravindra and Others (2002) 1 SCC 367
- Gayatri Balasamy v. ISG Novasoft Technologies Ltd. (2025) 7 SCC 1
- MMTC Ltd. v. Vedanta Ltd. (2019) 4 SCC 163
- Somdatt Builders-NCC-NEC (JV) v. National Highways Authority of India and Others (2025) 6 SCC 757
Provisions referred to
- Section 37(1)(c) of the Arbitration and Conciliation Act, 1996
- Section 34 of the Arbitration and Conciliation Act, 1996
- Section 31(7) of the Arbitration and Conciliation Act, 1996
- Section 17 of the Arbitration and Conciliation Act, 1996
- Section 13(1A) of the Commercial Courts Act, 2015
- Section 34 of the Code of Civil Procedure, 1908
Read the full judgment (PDF) ↗
Official source: High Court of Delhi. The PDF above is a copy from an open dataset of the court's public records.
This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.