Supreme Court: A State cannot recover alleged overpayment on old works from a contractor's bills under separate contracts

Court
Supreme Court of India
Date of judgment
30 September 2026
Case
C.A. No. 13299/2026
Parties
M/S. Awadhesh Singh Gautam Vs State Of Chhattisgarh
Outcome
Allowed

The court's decision

The Court examined each clause. Clause 44.1 of the General Conditions deals with liquidated damages for delay, capped at ten per cent of the initial contract price, and the recovery order was not based on any claim for delay. Clause 53.1(ii) applies only where a contract is terminated for the contractor's fundamental breach of defects-liability and five-year maintenance obligations, and there was nothing to show that either set of works had been terminated. Clause 7(iv) of the Integrity Pact permits recovery from dues under any other contract, but presupposes a prior determination that the bidder violated the pact, and the order neither mentions the pact nor records such a finding. Clause 38 is wide enough to allow recovery from other contracts once validly invoked, but only after a breach has been ascertained and the contractor told of it, which did not happen.

Clause 4.1 of the Special Conditions, on technical examination, alone answers the description of what the State did. But it allows recovery only from the security deposit or dues from the account of the very work audited, and it was undisputed that about Rs 1.07 crore remained due under the earlier works, which the State did not touch. It also requires that the contractor be given an opportunity to explain, that no recovery be made without the orders of the CEO of CGRRDA, and that action be initiated within twelve months of completion. No opportunity was given, the order was issued by the Executive Engineer alone without showing the CEO's approval, and nothing established the date of completion of the earlier works. None of the clauses, read singly or together, authorised the deduction or the manner of it.

The Court added that, however serious the allegations on the earlier works, until an overpayment is established in accordance with law it remains a disputed and unadjudicated claim for damages and not a debt due, as explained in Union of India v. Raman Iron Foundry. A party cannot treat it as an ascertained debt and appropriate sums otherwise payable under another contract. The recovery was in breach of the conditions of Clause 4.1 and in flagrant violation of natural justice. The High Court erred in declining relief on the ground of disputed facts, since the real question was whether the State could appropriate that disputed amount from money admittedly payable under three contracts unconnected with the earlier works, and that turns on the construction of the contract.

The recovery order of 27 September 2025 was quashed. The State must release Rs 84,17,003 with interest at 6 per cent a year from 27 September 2025 until payment. The State may still take appropriate proceedings in accordance with law to recover any amount ultimately found due on the earlier works. The observations are confined to the legality of the manner of recovery and do not affect the pending criminal case on Chargesheet No. 87 of 2025 or the correctness and quantum of the alleged overpayment. The appeals were allowed with no order as to costs.

Summary

The Supreme Court on 30 September 2026 quashed a recovery order by which a Chhattisgarh road agency had deducted Rs 84,17,003 from a contractor's bills on three ongoing road projects to make good an alleged overpayment on two earlier, separate contracts. A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe (judgment by Justice Aradhe) held that none of the contract clauses relied on by the State permitted this, and that the order was passed without notice, in breach of natural justice. It directed the State to release the amount with 6 per cent interest.

The appellant, M/s Awadhesh Singh Gautam, a partnership firm, was awarded three packages under the Pradhan Mantri Gram Sadak Yojana by the Chhattisgarh Rural Road Development Agency (CGRRDA), with work orders of 1 September 2023 and 5 November 2024. After doing about 40 per cent of each, it raised running bills of Rs 39,78,500, Rs 45,62,000 and Rs 23,55,000, which stayed unpaid despite reminders in September 2025. Separately, on 3 January 2023, it had been given two other road contracts of about Rs 437.43 lakh. After complaints of irregularities, a five-member committee appointed by the Collector, South Bastar, Dantewada, reported on 9 January 2024 that Rs 3,55,82,055 had been paid for those earlier works against work of only about Rs 1,54,75,938, an excess of Rs 2,01,06,117. It recommended recovery, blacklisting and a probe.

A demand note issued under Section 146 of the Chhattisgarh Land Revenue Code, 1959 was quashed by the High Court on 5 March 2025 for want of notice or hearing, leaving the State free to act afresh in accordance with law. An FIR was registered under Sections 420, 467, 468, 471, 409 and 120-B of the Indian Penal Code against a partner of the firm and CGRRDA officers, and a chargesheet was filed on 30 December 2025. Independently, the Executive Engineer of the Project Implementation Unit passed a recovery order on 27 September 2025, blocking Rs 84,17,003 out of the amounts payable and deducting Rs 28,00,000, Rs 38,00,000 and Rs 18,17,003 from the three subsequent works. The firm's representation of 9 October 2025 drew no response, and the High Court on 7 January 2026 dismissed its three writ petitions, saying disputed questions of fact could not be decided under Article 226.

The question before the court

What each side argued

Precedents referred to

Provisions referred to

Read the full judgment (PDF) ↗

Official source: Supreme Court of India. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

Government ContractsRecovery Of DuesNatural JusticeWrit JurisdictionContractor Payments

Related judgments

Delhi High Court Allowed ·18 Nov 2026 ·Tort ★ Editor's pick

Two Children Die After Falling into Open Sewer in Park; Delhi HC Directs DDA and DJB to Pay Compensation

The question: Whether a writ petition for compensation for deaths in an open sewer was maintainable despite the objection of disputed questions of fact and the remedy of a civil suit

The Delhi High Court has allowed two connected writ petitions, filed separately by the respective parent of each of two boys who died on 16 April 2010 after slipping into an open sewer manhole in a DDA park at SU Block, near Double Tanki, Pitampura. Justice Jasmeet Singh held the Delhi Development Authority and the Delhi Jal Board negligent and jointly and severally liable to pay Rs. 11,01,000 (rounded off) in each petition, with 9% simple interest from the date of filing of the petitions, and Rs. 1,00,000 as costs in each petition. The Municipal Corporation of Delhi was held not liable. The children were about 11 and a half years and 12 years nine months old. A PCR call led to FIR No. 142/2010, registered under Section 304A of the Indian Penal Code, 1860. The MCD and the Delhi Jal Board first denied that the site fell within their jurisdiction. In a reply of 22 June 2011 the Delhi Jal Board said the site was an RCC chamber with a raised wall of 4 to 5 feet. The police later filed a cancellation report, which, according to the police respondents, the ACMM, Rohini Courts, accepted on 5 August 2013. The parents learnt of this in 2015, sent notices under Section 80 of the Code of Civil Procedure seeking Rs. 10,00,000 each, and filed the writ petitions in 2016. They sought compensation, interest and costs from the DDA, Delhi Jal Board, MCD, the Investigating Officer, the Commissioner of Police and the Ministry of Home Affairs. The petitions were heard together and judgment, reserved on 13 August 2026, was pronounced on 18 November 2026.

W.P.(C)/317/2016 (with W.P.(C) 284/2016)
Kerala High Court Allowed ·20 Nov 2026 ·Preventive Detention ★ Editor's pick

Article 22(5) Violated by Non-Supply of Detention Order in Malayalam and Failure to Consider Representation: Kerala HC

The question: Whether unexplained delay in issuing the detention order snapped the live link with the last prejudicial activity

The Kerala High Court has set aside an order of preventive detention passed under Section 3(1) of the Prevention of Illicit Traffic in Narcotic Drugs and Psychotropic Substances Act, 1988 (PITNDPS Act), and the Government order confirming it for one year. A Division Bench of Justice Anil K. Narendran and Justice Muralee Krishna S. held that the detention order was not supplied to the detenue in Malayalam, the language recorded in it as known to him, and that a representation sent to the Central Government by the petitioner, his wife, was never considered. Each lapse breached Article 22(5) of the Constitution. The petitioner, wife of the detenue, challenged Ext.P1 order dated 31.03.2026, issued by the Additional Chief Secretary to the Government under Section 3(1), and Ext.P2 order dated 16.09.2026, issued under Section 9(f) read with Section 11, confirming the detention for one year from the date of detention. She also sought a writ of habeas corpus for his release. The detenue was apprehended on 16.07.2026 and has been in detention since 17.07.2026 in the Central Jail, Poojapura, Thiruvananthapuram. The detention order relied on three drug cases against the detenue, the last of which, Crime No.48 of 2025 of the Excise Enforcement and Anti Narcotic Special Squad, Kannur, arose from an incident on 24.06.2025. A fourth case, in which he had been convicted, was excluded. The Bench rejected the challenge based on delay and the snapping of the live link, and also found that all documents relied on had been supplied.

WP(Crl.) No. 1448 of 2026 | 2026:KER:88958
Bombay High Court Allowed ·19 Nov 2026 ·Land Acquisition

Bombay HC Remands CIDCO Land Acquisition References, Keeps Valuation Issue Subject to Pending Supreme Court Ruling

The question: What is the relevant date for fixing market value of land acquired under section 126 of the MRTP Act when the declaration came before the RFCTLARR Act and the award after it

The Bombay High Court at Aurangabad has allowed writ petitions filed by CIDCO and quashed a common order of the Maharashtra Land Acquisition, Rehabilitation and Resettlement Authority, Nagpur, dated 16/02/2019. The Authority had held that market value of land acquired under the Maharashtra Regional and Town Planning Act, 1966 (MRTP Act) had to be fixed as on 01/01/2014, the date the 2013 Act came into force, and had sent the matter back to the Land Acquisition Officer for a fresh award. The High Court held that the point is covered by Division Bench rulings in Sahebrao Bhausaheb Kalate v State of Maharashtra and S.N. Desai Hospitalities and Developers LLP v Deputy Collector, under which the relevant date is the date of the declaration under section 126(4) of the MRTP Act, here 22/12/2011. It also held that the Authority has no power to remand a reference to the Land Acquisition Officer. The lands in Gut Nos. 12, 14, 15, 16, 18 and 256 of Village Golwadi, Aurangabad, were acquired for CIDCO for the development of the Waluj area under section 126 of the MRTP Act read with section 6 of the Land Acquisition Act, 1894. The Special Land Acquisition Officer (Special Unit), Aurangabad passed an award on 21/02/2017 for the first set of lands and on 31/07/2018 for Gut No. 256. Unhappy with the compensation, the owners sought references under section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act). On a preliminary issue they argued that, since the declaration of 22/12/2011 pre-dated the 2013 Act and the award post-dated it, market value should be taken as on 01/01/2014. The Authority agreed.

WP No. 5134 of 2019 and connected petitions | 2026:BHC-AUG:55240