Gauhati HC: IOCL to verify and revoke terminations of bulk LPG work orders where RC was uploaded as its 15.01.2026 note allowed; rest stand

Court
Gauhati High Court
Date of judgment
5 October 2026
Case
WP(C)/2749/2026
Parties
RAMKRISHNA SUTRADHAR Vs THE UNION OF INDIA
Bench
HONOURABLE MR. JUSTICE KAUSHIK GOSWAMI
Outcome
Partly allowed

The court's decision

The Court framed the short question as the legality of the termination orders, whose primary ground was breach of the time limit in Corrigendum No. 3. The four months from the LoAs of 16.09.2025 expired on 15.01.2026. The Bench noted the Corrigendum's ATS mechanism and the reminders of 08.12.2025, 11.12.2025 and 07.01.2026.

The Court found that the final reminder of 15.01.2026 did not extend the deadline beyond 21:00 hours that day, but a note to it allowed a limited relaxation. Where the RC was already transferred and the PESO amendment application was filed but the licence awaited, the bidder could upload the updated RC with a copy of the application. Where no PESO application had been made, the bidder could upload the RC and state the expected completion date in the remarks column. The Bench held that the note must be read with the Corrigendum, and that IOCL could not approbate and reprobate. Neither the show-cause notices nor the termination orders dealt with it. For petitioners who had met its conditions, the orders showed non-application of mind and were arbitrary and unfair.

It was submitted at the bar that the petitioners in WP(C) Nos. 2749, 2751 and 2753 of 2026 uploaded their RCs with the PESO applications in time. In WP(C) No. 2755/2026, one of two ATS vehicles was in time, and the other's RC came four to five days late. In WP(C) Nos. 2750 and 2754 of 2026 the RCs came one to three days late. The judgment does not separately mention WP(C) No. 2747/2026. All petitioners eventually submitted the updated RCs and amended PESO licences.

For petitioners who did not upload the updated RC by 15.01.2026, the essential condition for the relaxation was missing. The Court said it cannot rewrite tender terms, that interference is warranted only for mala fides, favouritism or arbitrariness or irrationality of a degree no reasonable authority would reach, and that there was no such material for them. Later completion of formalities did not make their termination perverse. The argument on extensions to the earlier transporters failed: those were given with their consent, the LoAs were independent and conditional on the NIT and Corrigendum, and the NIT contemplated no provisional extensions.

The respondents were directed to verify whether each petitioner uploaded the RC, with the amended PESO licence or the stipulated PESO completion time as per the note, by 21:00 hours on 15.01.2026. Where so, the terminations of those work orders are to be revoked. Terminations for the rest continue. The exercise must be completed within one month of receipt of a certified copy of the order, and the petitions stand partly allowed and disposed of.

Summary

Justice Kaushik Goswami of the Gauhati High Court partly allowed seven writ petitions under Article 226 challenging the termination orders of 11.05.2026 by which work orders for transportation of bulk LPG in Assam and Meghalaya were terminated by Indian Oil Corporation Limited (IOCL). The Court held that termination was unsustainable for bidders who had uploaded the updated Registration Certificate (RC) of their Agreement to Sale (ATS) tank trucks, with the PESO amendment application or an expected completion date, by 21:00 hours on 15.01.2026, because the Corporation itself had carved out that relaxation in its final reminder e-mail of 15.01.2026 and the termination orders did not consider it. Bidders who did not upload the updated RC by that deadline got no relief.

The petitions are WP(C) Nos. 2747/2026 (Gaman Sarkar), 2749/2026 (Ramkrishna Sutradhar), 2750/2026 (Balo Ram Kaibarta), 2751/2026 (M/s Pallab Saikia), 2753/2026 (Laxmi Transport), 2754/2026 (Juri Thakuria) and 2755/2026 (Suresh Rabha). All arise from NIT No. LPG/BULK/TT/IOC/AS/2025-30 dated 01.03.2025. Corrigendum No. 3 dated 04.04.2025 let a bidder offer tank trucks still running under the existing contract through an ATS, but required the RC transfer and amended PESO licence within four months of the Letter of Acceptance (LoA), failing which the trucks could be terminated, and said the timeline would not be extended under any circumstances.

The petitioners were issued LoAs on 16.09.2025, so the period ended on 15.01.2026. Work orders followed and they began operating. Show-cause notices were issued on 05.03.2026 and the vehicles were suspended. After WP(C) No. 1526/2026 was disposed of on 27.04.2026 with a direction to decide their replies, IOCL terminated the work orders on 11.05.2026.

The question before the court

What each side argued

Precedents referred to

Provisions referred to

Read the full judgment (PDF) ↗

Official source: Gauhati High Court. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

TenderConstitutionalWrit JurisdictionContract

Related judgments

Delhi High Court Allowed ·18 Nov 2026 ·Tort ★ Editor's pick

Two Children Die After Falling into Open Sewer in Park; Delhi HC Directs DDA and DJB to Pay Compensation

The question: Whether a writ petition for compensation for deaths in an open sewer was maintainable despite the objection of disputed questions of fact and the remedy of a civil suit

The Delhi High Court has allowed two connected writ petitions, filed separately by the respective parent of each of two boys who died on 16 April 2010 after slipping into an open sewer manhole in a DDA park at SU Block, near Double Tanki, Pitampura. Justice Jasmeet Singh held the Delhi Development Authority and the Delhi Jal Board negligent and jointly and severally liable to pay Rs. 11,01,000 (rounded off) in each petition, with 9% simple interest from the date of filing of the petitions, and Rs. 1,00,000 as costs in each petition. The Municipal Corporation of Delhi was held not liable. The children were about 11 and a half years and 12 years nine months old. A PCR call led to FIR No. 142/2010, registered under Section 304A of the Indian Penal Code, 1860. The MCD and the Delhi Jal Board first denied that the site fell within their jurisdiction. In a reply of 22 June 2011 the Delhi Jal Board said the site was an RCC chamber with a raised wall of 4 to 5 feet. The police later filed a cancellation report, which, according to the police respondents, the ACMM, Rohini Courts, accepted on 5 August 2013. The parents learnt of this in 2015, sent notices under Section 80 of the Code of Civil Procedure seeking Rs. 10,00,000 each, and filed the writ petitions in 2016. They sought compensation, interest and costs from the DDA, Delhi Jal Board, MCD, the Investigating Officer, the Commissioner of Police and the Ministry of Home Affairs. The petitions were heard together and judgment, reserved on 13 August 2026, was pronounced on 18 November 2026.

W.P.(C)/317/2016 (with W.P.(C) 284/2016)
Kerala High Court Allowed ·20 Nov 2026 ·Preventive Detention ★ Editor's pick

Article 22(5) Violated by Non-Supply of Detention Order in Malayalam and Failure to Consider Representation: Kerala HC

The question: Whether unexplained delay in issuing the detention order snapped the live link with the last prejudicial activity

The Kerala High Court has set aside an order of preventive detention passed under Section 3(1) of the Prevention of Illicit Traffic in Narcotic Drugs and Psychotropic Substances Act, 1988 (PITNDPS Act), and the Government order confirming it for one year. A Division Bench of Justice Anil K. Narendran and Justice Muralee Krishna S. held that the detention order was not supplied to the detenue in Malayalam, the language recorded in it as known to him, and that a representation sent to the Central Government by the petitioner, his wife, was never considered. Each lapse breached Article 22(5) of the Constitution. The petitioner, wife of the detenue, challenged Ext.P1 order dated 31.03.2026, issued by the Additional Chief Secretary to the Government under Section 3(1), and Ext.P2 order dated 16.09.2026, issued under Section 9(f) read with Section 11, confirming the detention for one year from the date of detention. She also sought a writ of habeas corpus for his release. The detenue was apprehended on 16.07.2026 and has been in detention since 17.07.2026 in the Central Jail, Poojapura, Thiruvananthapuram. The detention order relied on three drug cases against the detenue, the last of which, Crime No.48 of 2025 of the Excise Enforcement and Anti Narcotic Special Squad, Kannur, arose from an incident on 24.06.2025. A fourth case, in which he had been convicted, was excluded. The Bench rejected the challenge based on delay and the snapping of the live link, and also found that all documents relied on had been supplied.

WP(Crl.) No. 1448 of 2026 | 2026:KER:88958
Bombay High Court Allowed ·19 Nov 2026 ·Land Acquisition

Bombay HC Remands CIDCO Land Acquisition References, Keeps Valuation Issue Subject to Pending Supreme Court Ruling

The question: What is the relevant date for fixing market value of land acquired under section 126 of the MRTP Act when the declaration came before the RFCTLARR Act and the award after it

The Bombay High Court at Aurangabad has allowed writ petitions filed by CIDCO and quashed a common order of the Maharashtra Land Acquisition, Rehabilitation and Resettlement Authority, Nagpur, dated 16/02/2019. The Authority had held that market value of land acquired under the Maharashtra Regional and Town Planning Act, 1966 (MRTP Act) had to be fixed as on 01/01/2014, the date the 2013 Act came into force, and had sent the matter back to the Land Acquisition Officer for a fresh award. The High Court held that the point is covered by Division Bench rulings in Sahebrao Bhausaheb Kalate v State of Maharashtra and S.N. Desai Hospitalities and Developers LLP v Deputy Collector, under which the relevant date is the date of the declaration under section 126(4) of the MRTP Act, here 22/12/2011. It also held that the Authority has no power to remand a reference to the Land Acquisition Officer. The lands in Gut Nos. 12, 14, 15, 16, 18 and 256 of Village Golwadi, Aurangabad, were acquired for CIDCO for the development of the Waluj area under section 126 of the MRTP Act read with section 6 of the Land Acquisition Act, 1894. The Special Land Acquisition Officer (Special Unit), Aurangabad passed an award on 21/02/2017 for the first set of lands and on 31/07/2018 for Gut No. 256. Unhappy with the compensation, the owners sought references under section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act). On a preliminary issue they argued that, since the declaration of 22/12/2011 pre-dated the 2013 Act and the award post-dated it, market value should be taken as on 01/01/2014. The Authority agreed.

WP No. 5134 of 2019 and connected petitions | 2026:BHC-AUG:55240