Chhattisgarh High Court Allowed ·29 Oct 2026 ·Service Law

Chhattisgarh High Court quashes CRPF Inspector's removal ordered while he was in jail; reinstatement without back wages

The question: Whether a removal order passed after an enquiry held while the employee was in jail, without hearing him, violates natural justice

The High Court of Chhattisgarh has set aside the removal from service of a Central Reserve Police Force Inspector, holding that the departmental enquiry against him was conducted behind his back while he was an undertrial prisoner and that he was never given a hearing. Justice Amitendra Kishore Prasad quashed the removal order dated 03.09.2018 and the appellate order dated 11.05.2022, and directed reinstatement in accordance with law, without back wages. The respondents remain free to start fresh departmental proceedings in accordance with law. The petitioner was undergoing training at the Anti-Naxal Training Centre, Ambikapur, when he allegedly had a physical altercation on 02.08.2015 with a civilian, who died of his injuries on 11.10.2015. An FIR was registered under Sections 294, 506, 323 and 302 of the IPC. He was arrested in 2016, a departmental enquiry followed for alleged violation of the Conduct Rules, and the Deputy Inspector General removed him from service on 03.09.2018. He was released on bail on 05.11.2018 and acquitted by the 3rd Additional Sessions Judge, Ambikapur, on 01.11.2021, on the benefit of doubt. Thereafter he approached the appellate authority under Section 11(1) of the Central Reserve Police Force Act, 1949 read with Rule 27 of the Central Reserve Police Force Rules, 1955, seeking reinstatement on the ground of his acquittal. The judgment describes this as an appeal and elsewhere as an application/appeal, and records that it was rejected on 11.05.2022. He then filed the present writ petition seeking quashing of both orders and reinstatement with consequential benefits.

WP(S) No. 8456 of 2022 | 2026:CGHC:45683
Telangana High Court Allowed ·11 Nov 2026 ·Criminal

Cannot Send a Person to Jail Without First Giving a Real Opportunity to Respond: Telangana High Court Sets Aside Warrant

The question: Whether a warrant of commitment for breach of a good-behaviour bond under Section 141 of the BNSS could stand when service of the notice was not shown and the warrant was issued on the day of the show-cause notice

The Telangana High Court has set aside a warrant of commitment issued by a Tahsildar-cum-Executive Magistrate against a man who was sent to prison for alleged breach of a bond for good behaviour under Section 141 of the Bharatiya Nagarik Suraksha Sanhita, 2023. Justice N. Tukaramji allowed a writ petition filed by the man's wife and directed that he be released forthwith, unless his detention is required in connection with any other case or lawful order. The Court found that the material on record did not disclose that the notice proposing forfeiture had been properly served, and that the commitment warrant was issued on the same day as the show-cause notice, without waiting for a reply. It also noted that, on this Court's consistent view, the mere registration of a crime is not conclusive proof of breach of such a bond. The Court made clear that its order does not preclude the competent authority from initiating appropriate proceedings, if warranted, at the appropriate stage, strictly in accordance with the procedure prescribed by law. The petition, Writ Petition No. 36623 of 2026, was filed under Article 226 of the Constitution by Palle Himabindu. It challenged the order of forfeiture of bond and detention dated 09.10.2026, passed in M.C. No. 11 of 2026 by the Tahasildhar cum Executive Magistrate, Narsampet Mandal, Warangal District, against her husband, Palle Prashanth. The petition pleaded that no notice was issued, no explanation was called for, and the whole process was completed on 09.10.2026 itself on the influence of the de facto complainant, a revenue employee. It also pleaded violation of natural justice and of Articles 14 and 19(1)(g). By I.A. No. 1 of 2026 the petitioner prayed that the operation of the impugned order be suspended, by releasing him from the Jail (Sub-Jail, Mahabubabad), till the disposal of the writ petition. The judgment records that the husband had executed a bond for maintaining good behaviour for one year, together with a surety, before the Mandal Executive Magistrate, Narsampet. A report of the Station House Officer, Narsampet Police Station, showed that a crime had been registered against him alleging an offence. On that report the Executive Magistrate issued a notice proposing forfeiture of the bond, and then the warrant of commitment.

WP/36623/2026
Supreme Court Allowed ·30 Sep 2026 ·Government Contracts

Supreme Court: A State cannot recover alleged overpayment on old works from a contractor's bills under separate contracts

The question: Is the recovery order traceable to any clause of the contract that lets the State recover dues of one contract from payments under another?

The Supreme Court on 30 September 2026 quashed a recovery order by which a Chhattisgarh road agency had deducted Rs 84,17,003 from a contractor's bills on three ongoing road projects to make good an alleged overpayment on two earlier, separate contracts. A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe (judgment by Justice Aradhe) held that none of the contract clauses relied on by the State permitted this, and that the order was passed without notice, in breach of natural justice. It directed the State to release the amount with 6 per cent interest. The appellant, M/s Awadhesh Singh Gautam, a partnership firm, was awarded three packages under the Pradhan Mantri Gram Sadak Yojana by the Chhattisgarh Rural Road Development Agency (CGRRDA), with work orders of 1 September 2023 and 5 November 2024. After doing about 40 per cent of each, it raised running bills of Rs 39,78,500, Rs 45,62,000 and Rs 23,55,000, which stayed unpaid despite reminders in September 2025. Separately, on 3 January 2023, it had been given two other road contracts of about Rs 437.43 lakh. After complaints of irregularities, a five-member committee appointed by the Collector, South Bastar, Dantewada, reported on 9 January 2024 that Rs 3,55,82,055 had been paid for those earlier works against work of only about Rs 1,54,75,938, an excess of Rs 2,01,06,117. It recommended recovery, blacklisting and a probe. A demand note issued under Section 146 of the Chhattisgarh Land Revenue Code, 1959 was quashed by the High Court on 5 March 2025 for want of notice or hearing, leaving the State free to act afresh in accordance with law. An FIR was registered under Sections 420, 467, 468, 471, 409 and 120-B of the Indian Penal Code against a partner of the firm and CGRRDA officers, and a chargesheet was filed on 30 December 2025. Independently, the Executive Engineer of the Project Implementation Unit passed a recovery order on 27 September 2025, blocking Rs 84,17,003 out of the amounts payable and deducting Rs 28,00,000, Rs 38,00,000 and Rs 18,17,003 from the three subsequent works. The firm's representation of 9 October 2025 drew no response, and the High Court on 7 January 2026 dismissed its three writ petitions, saying disputed questions of fact could not be decided under Article 226.

C.A. No. 13299/2026