Subscribe

Latest › Delhi High Court › Civil › Contract & Commercial › 28 September 2026

Delhi High Court Notable

Delhi HC: Arbitrator's refusal of price variation despite the contract's formula is patent illegality; award partly set aside

Court
High Court of Delhi
Date of judgment
28 September 2026
Case
O.M.P. (COMM)/182/2019
Parties
M/S. DWARIKA PROJECTS LTD. Vs NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY
Bench
Mini Pushkarna
Outcome
Partly allowed

Summary

The Delhi High Court has set aside part of an arbitral award in a road-bridge contract with the New Okhla Industrial Development Authority (NOIDA), holding that the arbitrator's refusal of the contractor's price variation claim was patently illegal because it ignored what the contract itself provides. Justice Mini Pushkarna held that the contract allowed price variation both for the original period and for an extension caused by the contractor's own delay, and that the arbitrator had in effect rewritten the contract. The Court, however, upheld his finding that the delay was the contractor's fault.

Dwarika Projects Ltd. won a tender for the construction of Bridge No. 2 on an irrigation drain between Sectors 78 and 49, Noida, under a contract of 7 December 2009 that required completion within twelve months. The work finished much later, and each side blamed the other. The sole arbitrator's award of 10 December 2018 awarded the contractor Rs 1,02,95,056 on Claims 1, 2 (in part) and 3, with interest and costs, but rejected Claims 4 to 10. The contractor's petition under Section 34 of the Arbitration and Conciliation Act, 1996 was finally confined to Claim 4, its claim of Rs 2,29,43,350 for price variation.

The Court set the award aside to that extent and left the parties free to start fresh arbitration to work out the amount.

The question before the court

What each side argued

The court's decision

The Court first set out the limits of Section 34: it is not an appeal, and it does not allow reappreciation of evidence or substitution of a Court's view, but an award can be set aside for patent illegality, including where the arbitrator ignores specific provisions of the contract or takes a view that is not even a possible one.

Original period: the arbitrator had held that Clause 50.1 made the Bill of Quantities rates hold good till completion, so no price variation was available. The Court said he read only the first part of the clause and ignored the qualifying words, even though Clause 50.2 provides a price variation formula for labour, material and fuel, and the tender documents say the quoted prices were subject to adjustment under the Special Conditions. This was not another interpretation but one that made the agreed procedure inoperative, so it was not a possible view.

Extended period: the arbitrator himself noted that Clause 51.2, read with Clause 7.5, allows price variation even where the extension is for the contractor's delay, but then held that the contractor's delay barred it. The Court said the contract distinguishes only how price variation is calculated (the indices on the last date of the original period where the delay is the contractor's), not whether it is payable. Treating delay as a complete bar rewrote the contract and went to the root of the matter. Ramnath International was distinguished, because the contract there expressly barred compensation for extensions, while this one has no such bar.

Delay: the Court upheld the finding that the delay was attributable to the contractor. Electric poles stood on one side of the drain only and were removed on 7 May 2010, with no proof of complete stoppage. No term required SAIL steel, and NOIDA's letter of 21 March 2011 allowed other brands. The arbitrator found no delay in paying bills, and NOIDA's letters from 2010 and 2011 on the slow pace of work were not challenged.

Order: the award was set aside to the extent of Claim 4 for patent illegality, and the parties are at liberty to invoke fresh arbitration to determine the amount of price variation. The petition was partly allowed.

Precedents referred to

Provisions referred to

Read the full judgment (PDF) ↗

Official source: High Court of Delhi. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

ArbitrationConstruction ContractsPrice VariationPatent Illegality

Related judgments

Supreme Court ·28 Sep 2026 ·Insolvency ★ Editor's pick

Supreme Court: A liquidation-auction bidder who misses the payment deadline cannot get its deposit back

The question: Can a successful bidder in an IBC liquidation auction get a refund after failing to pay the balance price within the stipulated period?

The Supreme Court on 28 September 2026 dismissed an appeal by ASJ Finsolutions Pvt. Ltd., the successful bidder for a Haryana land parcel in a corporate liquidation auction, which had asked for a refund of the money it deposited after it failed to pay the balance price within the time allowed. A bench of Justices J.B. Pardiwala and K. Vinod Chandran (judgment by Justice Vinod Chandran) agreed with the National Company Law Appellate Tribunal that the forfeiture was a necessary consequence of the default under the e-auction notice. Lot No. 5, a parcel at Village Nangal Khurd, Tehsil Sonepat, with a reserve price of Rs 25.56 crore, was auctioned on 15 November 2021 in the liquidation of a company, under an e-auction notice of 25 October 2021. The notice said the sale was on an 'as is where is' basis and carried a note that a civil suit was pending over the sale deed of part of the land. The appellant bid at the reserve price and won. It paid Rs 6.39 crore, being 25 per cent of the bid, which included earnest money of Rs 2.55 crore and Rs 3.84 crore towards the balance. The balance of Rs 19.17 crore was due within 30 days, that is by 14 December 2021, or within 90 days with interest at 12 per cent, that is by 14 February 2022. The day after the 30 days ended, the appellant e-mailed the liquidator that it would pay by 14 February 2022 with interest, but it did not pay. On 11 February 2022 it asked the NCLT for the earlier title deeds, and that application was rejected on 31 March 2023, with an appeal dismissed on 21 April 2023. While its writ petition in the Punjab and Haryana High Court was pending, the property was re-auctioned for Rs 31.10 crore, which is Rs 5.54 crore more than the appellant's bid. After the High Court rejected its prayer but left it free to pursue other remedies, the appellant sought to annul the forfeiture of its earnest money and get a refund. The NCLT allowed that, the NCLAT reversed it, and the appellant came to the Supreme Court.

Dismissed C.A. No. 13023/2025
Supreme Court ·28 Sep 2026 ·Service Law

Supreme Court: Bihar and Jharkhand must pay Rs 1 lakh each to daily-wage staff of five defunct corporations, with interest

The question: How should the remaining, untraced employees and legal heirs be dealt with, and can the exercise be closed?

The Supreme Court on 28 September 2026 settled the last three open issues in a long-running writ petition by the employees' federation of five defunct State-owned corporations of undivided Bihar. A bench of Justices Vikram Nath and Sandeep Mehta (judgment by Justice Mehta) directed the States of Bihar and Jharkhand to pay a one-time Rs 1,00,000 to each daily-wage employee or workman, to pay simple interest on delayed dues (12 per cent a year on provident fund dues and 6 per cent on salary and other dues), and to publish particulars of all employees and the status of their claims. It also closed the identification exercise, while giving untraced claimants 12 months to come forward. The Court stressed that these reliefs rest on the peculiar facts and are not a general rule. The case goes back to the reorganisation of Bihar under the Bihar Reorganisation Act, 2000, which created Jharkhand and raised questions about the dues and service claims of the employees of five inter-State corporations: the Bihar State Construction Corporation, the Bihar State Industrial Development Corporation, the Bihar State Electronic Development Corporation, the Bihar State Forest Development Corporation and the Bihar State Panchayati Raj Financial Corporation. After years of litigation, including Kapila Hingorani v. State of Bihar, the Court set up a Committee under Justice Dinesh Maheshwari, a retired Supreme Court judge. By an order of 29 May 2026 it accepted the Committee's Final Report of 30 April 2026 to the extent indicated, and left three issues open. In August 2026 the two States filed compliance affidavits. Of 2,274 verified employees and workmen, dues had been fully paid to 2,074, and about 200 cases remained pending because the claimants were untraceable or lacked documents. The three issues left open were: identification and verification of the remaining employees and heirs; the entitlement of daily-wage workmen and the heirs of the deceased to lump-sum compensation or other support; and the entitlement to, and rate of, interest on delayed salaries, retiral dues and provident fund amounts.

Disposed of W.P.(C) No. 932/2022
AP High Court ·28 Sep 2026 ·Police Powers

AP High Court: Police cannot keep a 'suspect sheet' on a person facing a single case without showing habitual offending

The question: Can a suspect sheet be opened and continued against a person who faces only one criminal case?

A man who had been named in one criminal case asked the High Court to close a suspect sheet the Visakhapatnam police opened against him in 2019. The police said the sheet was meant to curb his alleged unlawful activity near the Steel Plant. The High Court held that this general claim was not enough, because nothing showed he fell within the categories in the Police Standing Orders or was a habitual offender.

Allowed WP/4108/2023