Subscribe

Latest › Supreme Court › Civil › Civil Procedure & Limitation › 13 July 2026

Supreme Court Notable

Supreme Court: Plaintiffs in commercial suits must answer a counter-claim within 30 days, extendable to 120 at most

Court
Supreme Court of India
Date of judgment
13 July 2026
Case
2026 INSC 684
Parties
A.K. GHOSH & COMPANY AND OTHERS Vs BIMAN BOSE AND OTHERS
Bench
SANJAY KUMAR
Outcome
Dismissed

Summary

The Supreme Court on 13 July 2026 held that the strict time limits for a written statement in a commercial suit also bind a plaintiff who replies to a defendant's counter-claim. A bench of Justices Sanjay Kumar and K. Vinod Chandran (judgment by Justice Sanjay Kumar) held that the proviso to Order VIII Rule 1 of the Code of Civil Procedure, as applied to commercial suits, requires such a reply ordinarily within 30 days, with the court able to extend that, for sufficient cause and on costs, but never beyond 120 days. It also held that an order refusing leave to file a belated reply cannot be appealed under Section 13(1A) of the Commercial Courts Act, 2015. It dismissed the plaintiffs' appeals.

The plaintiffs, A.K. Ghosh & Company and others, had supplied printing paper to the defendants. After a dispute over payment, they served a legal notice dated 16 June 2021 claiming Rs 74,65,527 with interest, which the defendants denied on 28 June 2021. They then filed a recovery suit in the Calcutta High Court, later renumbered CS (COM) No. 440 of 2024. The contesting defendants (Nos. 1, 2, 3, 5 and 6) filed a written statement and a counter-claim, copies of which were served on the plaintiffs' Advocate-on-Record under a letter dated 18 July 2023.

The plaintiffs applied for leave to file their written statement to the counter-claim only on 15 March 2024, after 238 days. A Single Judge dismissed the application on 19 August 2024, reasoning that Order VIII Rule 6G applies the rules for a defendant's written statement to a reply to a counter-claim, so the plaintiffs could not escape the time frame under Order VIII Rule 1 as applied to commercial suits. A Division Bench dismissed their appeal on 26 February 2025, both as not maintainable and on merits. This Court stayed the suit on 23 May 2025 and heard the appeals.

The question before the court

What each side argued

The court's decision

The Court said the issue turns on the interpretation of Order VIII CPC. A counter-claim, introduced by the 1976 amendment through Rule 6A, is on par with a plaint, and the plaintiff's reply is nothing other than his written statement. Rule 6A(3) lets the court fix the time for that reply, Rule 6E allows judgment against a plaintiff who defaults, and Rule 6G applies the rules on a defendant's written statement to such a reply. The time limit for a defendant has been tightened over the years. The proviso to Rule 1, as substituted for commercial suits by Section 16 of the Commercial Courts Act and its Schedule, allows a defendant 30 days and, for reasons recorded and on costs, up to 120 days, after which the right to file is forfeited. This was affirmed in SCG Contracts (India) Private Limited v. K.S. Chamankar Infrastructure Private Limited. Rule 10 and its proviso stress that no court may extend the time beyond that limit.

The Court noted that some High Courts had taken a liberal view. The Rajasthan High Court (Nirottam Sharma) held that the trial court must fix a time under Rule 6A(3). The Madras High Court (CSCO LLC v. Lakshmi Saraswathi Spintex) condoned a 563-day delay, reasoning that no time had been fixed and that SCG Contracts did not apply, and also held that the clock starts only when the court fixes a time, and that the bar in the proviso to Rule 10 mentions Rule 1 but not Rule 9, so a written statement to a counter-claim could be extended. The Bombay High Court (Dattaram Pednekar, following Shalini Nunes Mascarenhas) held that Rule 6G concerns only the contents of a written statement. The Delhi High Court's Indcon Boiler decision turned on its own facts. The Court disagreed with the Bombay view, saying the phrasing of Rule 6G admits no such restriction, and it held that the Madras view would leave a plaintiff free to devise his own time schedule if the court failed to fix one. That could not be the intention of the statute, which in commercial suits seeks speedy disposal, and tighter time lines are consistent with that object. A reply to a counter-claim is also not a 'subsequent pleading' needing leave under Rule 9, which excepts a defence to a set-off or counter-claim.

Read together, the scheme is that the court may first fix a time under Rule 6A(3). That time may be extended on the plaintiff's application under the proviso to Rule 1 read with Rule 6G, up to a maximum of 120 days from service of summons or receipt of the counter-claim, or by the court itself under Rule 9, where the time it fixes is shorter, just 30 days, within the same outer limit. The Court answered the question in the affirmative. The plaintiffs' application came after 238 days, far beyond the outer limit of 120 days.

On maintainability, the Court reviewed Section 13 of the Commercial Courts Act. The proviso to Section 13(1A) allows an appeal only from orders enumerated in Order XLIII CPC and Section 37 of the Arbitration and Conciliation Act, 1996, and Section 13(2) says that no appeal shall lie otherwise than in accordance with the Act. Relying on BGS SGS SOMA JV v. NHPC Limited, a three-Judge Bench decision that an appeal is a creature of statute, and Kandla Export Corporation v. OCI Corporation, it held that an order under Order VIII is not appealable under Order XLIII, so the Division Bench was right that the appeal was not even maintainable.

The Judge and the Division Bench were fully justified in rejecting the plea for leave despite the long delay. The appeals were dismissed, the interim order of 23 May 2025 was vacated, pending applications were dismissed and the parties bear their own costs.

Precedents referred to

Provisions referred to

Read the full judgment (PDF) ↗

Official source: Supreme Court of India. The PDF above is a copy from an open dataset of the court's public records.

This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.

Commercial CourtsCivil ProcedureCounter-ClaimLimitationWritten Statement

Related judgments

Supreme Court ·29 Sep 2026 ·Civil Procedure ★ Editor's pick

Supreme Court: Fresh suit for specific performance barred under Order II Rule 2 where the first suit sought only an injunction

The question: Is a second suit for specific performance barred by Order II Rule 2 CPC when the first suit sought only an injunction and was withdrawn with a request for liberty to file afresh?

The Supreme Court on 29 September 2026 set aside concurrent decrees for specific performance of an alleged oral agreement to sell land and dismissed the suit on two independent grounds. A bench of Justices J.B. Pardiwala and K. Vinod Chandran (judgment by Justice Vinod Chandran) held that the second suit was barred by Order II Rule 2 of the Code of Civil Procedure, because the plaintiff had earlier sued only for an injunction on the same oral contract, when the right to seek specific performance had already arisen, and had not obtained leave. It also held, for completeness, that the plaintiff had failed to prove a concluded oral contract. The plaintiffs, J P Iscon Private Ltd. and another, said they had struck an oral bargain with the first defendant company and others to buy a property. The price was said to have been fixed at Rs 18.51 crore, with a token advance, and then raised to Rs 20.50 crore at the defendants' insistence, with Rs 5,11,000 paid in cash and a cheque of Rs 5 crore handed over in January 2007. They first filed a suit at Mirzapur seeking only a permanent injunction against alienation of the property, and withdrew it on the footing of settlement talks, after which they filed the present suit for specific performance in 2007. The pleadings were amended in 2011. The Trial Court and the High Court decreed the suit, and the defendants, Bombay Garage Ahmedabad Limited and others, appealed.

Set aside C.A. No. 13255/2026
AP High Court ·25 Sep 2026 ·Civil Law

AP High Court: Plaint cannot be struck out as time-barred without trial where an insolvency petition may acknowledge the debt

The question: Can mention of a creditor and the amount due in the debtor's insolvency petition amount to an acknowledgment under Section 18 of the Limitation Act?

A lender sued to recover Rs 4 lakh on a 2021 promissory note. The trial court at Jammalamadugu rejected the plaint as time-barred, because the debtor's later insolvency petition listing the lender as a creditor was, it said, only an admission and not an acknowledgment that extends limitation. The High Court set that order aside and sent the case back.

Disposed of CRP/2609/2026
Telangana High Court ·22 Sep 2026 ·Land Law

Telangana HC: State cannot reopen 1960 land assignment decades later without proving it was assigned land

The question: Could the RDO treat a Tahsildar's letter as an appeal 1,460 days after the Tahsildar's order, when Section 4-A allows 90 days?

The State appealed against a Single Judge's order quashing a 2020 resumption of about 13 acres in Nizampet village, Medchal-Malkajgiri district, under the Telangana Assignment (Prohibition of Transfers) Act, 1977. A Division Bench of the High Court dismissed three connected writ appeals, holding that the State acted far too late and could not show the land was assigned land with a bar on transfers.

Dismissed WA/781/2026