Latest › Supreme Court › Civil › Civil Procedure & Limitation › 13 July 2026
Supreme Court: Plaintiffs in commercial suits must answer a counter-claim within 30 days, extendable to 120 at most
- Court
- Supreme Court of India
- Date of judgment
- 13 July 2026
- Case
- 2026 INSC 684
- Parties
- A.K. GHOSH & COMPANY AND OTHERS Vs BIMAN BOSE AND OTHERS
- Bench
- SANJAY KUMAR
- Outcome
- Dismissed
Summary
The Supreme Court on 13 July 2026 held that the strict time limits for a written statement in a commercial suit also bind a plaintiff who replies to a defendant's counter-claim. A bench of Justices Sanjay Kumar and K. Vinod Chandran (judgment by Justice Sanjay Kumar) held that the proviso to Order VIII Rule 1 of the Code of Civil Procedure, as applied to commercial suits, requires such a reply ordinarily within 30 days, with the court able to extend that, for sufficient cause and on costs, but never beyond 120 days. It also held that an order refusing leave to file a belated reply cannot be appealed under Section 13(1A) of the Commercial Courts Act, 2015. It dismissed the plaintiffs' appeals.
The plaintiffs, A.K. Ghosh & Company and others, had supplied printing paper to the defendants. After a dispute over payment, they served a legal notice dated 16 June 2021 claiming Rs 74,65,527 with interest, which the defendants denied on 28 June 2021. They then filed a recovery suit in the Calcutta High Court, later renumbered CS (COM) No. 440 of 2024. The contesting defendants (Nos. 1, 2, 3, 5 and 6) filed a written statement and a counter-claim, copies of which were served on the plaintiffs' Advocate-on-Record under a letter dated 18 July 2023.
The plaintiffs applied for leave to file their written statement to the counter-claim only on 15 March 2024, after 238 days. A Single Judge dismissed the application on 19 August 2024, reasoning that Order VIII Rule 6G applies the rules for a defendant's written statement to a reply to a counter-claim, so the plaintiffs could not escape the time frame under Order VIII Rule 1 as applied to commercial suits. A Division Bench dismissed their appeal on 26 February 2025, both as not maintainable and on merits. This Court stayed the suit on 23 May 2025 and heard the appeals.
The question before the court
- Does the mandatory time frame in the proviso to Order VIII Rule 1 CPC apply to a plaintiff's written statement in reply to a defendant's counter-claim in a commercial suit?
- Is an appeal under Section 13(1A) of the Commercial Courts Act maintainable against an order refusing to take such a reply on record?
What each side argued
- For the plaintiffs: the 120-day period for a defendant's written statement cannot be applied mutatis mutandis to a plaintiff's reply to a counter-claim. No time had been fixed by the Judge under Order VIII Rule 6A(3), so the plaintiffs could not be penalised by being denied an opportunity to respond, and a penal provision must be read in favour of the party it is used against. On maintainability, they argued that Section 13(2) of the Commercial Courts Act only regulates the procedure for appeals and cannot be read to bar every appeal not expressly provided in the Act. They relied on Nasima Naqi v. Todi Tea Company on what a statute leaves out being excluded.
- For the contesting defendants: the amended Order VIII leaves no doubt that a written statement in response to a counter-claim must follow the same time frame. Order VIII Rule 6G says that the rules relating to a defendant's written statement apply to a written statement in answer to a counter-claim, so the time limit in Order VIII Rule 1 applies squarely.
The court's decision
The Court said the issue turns on the interpretation of Order VIII CPC. A counter-claim, introduced by the 1976 amendment through Rule 6A, is on par with a plaint, and the plaintiff's reply is nothing other than his written statement. Rule 6A(3) lets the court fix the time for that reply, Rule 6E allows judgment against a plaintiff who defaults, and Rule 6G applies the rules on a defendant's written statement to such a reply. The time limit for a defendant has been tightened over the years. The proviso to Rule 1, as substituted for commercial suits by Section 16 of the Commercial Courts Act and its Schedule, allows a defendant 30 days and, for reasons recorded and on costs, up to 120 days, after which the right to file is forfeited. This was affirmed in SCG Contracts (India) Private Limited v. K.S. Chamankar Infrastructure Private Limited. Rule 10 and its proviso stress that no court may extend the time beyond that limit.
The Court noted that some High Courts had taken a liberal view. The Rajasthan High Court (Nirottam Sharma) held that the trial court must fix a time under Rule 6A(3). The Madras High Court (CSCO LLC v. Lakshmi Saraswathi Spintex) condoned a 563-day delay, reasoning that no time had been fixed and that SCG Contracts did not apply, and also held that the clock starts only when the court fixes a time, and that the bar in the proviso to Rule 10 mentions Rule 1 but not Rule 9, so a written statement to a counter-claim could be extended. The Bombay High Court (Dattaram Pednekar, following Shalini Nunes Mascarenhas) held that Rule 6G concerns only the contents of a written statement. The Delhi High Court's Indcon Boiler decision turned on its own facts. The Court disagreed with the Bombay view, saying the phrasing of Rule 6G admits no such restriction, and it held that the Madras view would leave a plaintiff free to devise his own time schedule if the court failed to fix one. That could not be the intention of the statute, which in commercial suits seeks speedy disposal, and tighter time lines are consistent with that object. A reply to a counter-claim is also not a 'subsequent pleading' needing leave under Rule 9, which excepts a defence to a set-off or counter-claim.
Read together, the scheme is that the court may first fix a time under Rule 6A(3). That time may be extended on the plaintiff's application under the proviso to Rule 1 read with Rule 6G, up to a maximum of 120 days from service of summons or receipt of the counter-claim, or by the court itself under Rule 9, where the time it fixes is shorter, just 30 days, within the same outer limit. The Court answered the question in the affirmative. The plaintiffs' application came after 238 days, far beyond the outer limit of 120 days.
On maintainability, the Court reviewed Section 13 of the Commercial Courts Act. The proviso to Section 13(1A) allows an appeal only from orders enumerated in Order XLIII CPC and Section 37 of the Arbitration and Conciliation Act, 1996, and Section 13(2) says that no appeal shall lie otherwise than in accordance with the Act. Relying on BGS SGS SOMA JV v. NHPC Limited, a three-Judge Bench decision that an appeal is a creature of statute, and Kandla Export Corporation v. OCI Corporation, it held that an order under Order VIII is not appealable under Order XLIII, so the Division Bench was right that the appeal was not even maintainable.
The Judge and the Division Bench were fully justified in rejecting the plea for leave despite the long delay. The appeals were dismissed, the interim order of 23 May 2025 was vacated, pending applications were dismissed and the parties bear their own costs.
Precedents referred to
- SCG Contracts (India) Private Limited v. K.S. Chamankar Infrastructure Private Limited, (2019) 12 SCC 210
- BGS SGS SOMA JV v. NHPC Limited, (2020) 4 SCC 234 (three-Judge Bench)
- Kandla Export Corporation v. OCI Corporation, (2018) 14 SCC 715
- Nasima Naqi v. Todi Tea Company Limited, (2023) 17 SCC 641
- Nirottam Sharma v. Ramkishore (Rajasthan High Court, 7 February 2018) (a 'liberal' view, noted by the Court)
- CSCO LLC v. Lakshmi Saraswathi Spintex Limited (Madras High Court, 28 January 2022) (not followed)
- Dattaram Krishnanath Pednekar v. Pandurang K. Pednekar, 2010 (7) Mh.L.J. 386 (Bombay High Court) (not followed)
- Mrs. Shalini Nunes Mascarenhas v. Mr. Trevor Nunes, 2009 (2) Goa LR 222 (not followed)
Provisions referred to
- Order VIII Rules 1, 6A, 6E, 6G, 9 and 10, Code of Civil Procedure, 1908
- Sections 13 and 16, Commercial Courts Act, 2015
- Order XLIII, Code of Civil Procedure, 1908
- Section 37, Arbitration and Conciliation Act, 1996
Read the full judgment (PDF) ↗
Official source: Supreme Court of India. The PDF above is a copy from an open dataset of the court's public records.
This summary is prepared for general assistance only. It may contain errors and is not legal advice — rely on the full judgment.